History and Plans

2011: Site selection, negotiations with land owner, lease signed and grid connection offer secured

March 2012: Planning application submitted

June 2012: Planning permission granted

September 2013: Finance and turbine procurement

February 2014: Access track, turbine foundation and grid connection completed

March 2014: Turbine delivered and installed

April 2014: Site fully operational